Taipingling Nuclear Power Plant
| Taipingling Nuclear Power Plant | |
|---|---|
![]() | |
| Country | People's Republic of China |
| Location | Huangbu, Huidong, Guangdong |
| Coordinates | 22°41′40″N 114°59′00″E / 22.69444°N 114.98333°E |
| Status | Operational |
| Construction began | 2019 |
| Construction cost | US$12.1 billion |
| Owner | CGN Huizhou Nuclear Power |
| Operator | CGN Huizhou Nuclear Power |
| Nuclear power station | |
| Reactor type | Hualong One PWR |
| Power generation | |
| Units operational | 2 × 1116 MWe |
| Units planned | 2 × 1116 MWe |
| Units under const. | 2 × 1116 MWe |
The Taipingling Nuclear Power Plant is a nuclear power station under construction in Huangbu Town, Huidong County, Huizhou city on the coast of Guangdong Province, in southeast China. The plant is owned by CGN Huizhou Nuclear Power Co. CGN originally planned to have AP1000 light water reactors, but later changed plans to the Hualong One design.[1]
Approval for the plant was granted in February 2019 and first concrete for Unit 1 was poured in December 2019. Unit 1 began commercial operation in April 2026.[2]
Approval for units 3 and 4 was granted in December 2023.[3] First concrete for Unit 3 was poured in June 2025.[4]
On May 3, 2026, Unit 2 successfully completed its first fuel loading, and officially entering the nuclear commissioning phase, and connected to grid on July 4, 2026.[5], began commercial operation in August 3, 2026.[6]
In August 2026, China's State Council approved the construction of 4 Hualong One & two Huanlong One 2.0 units for Jinqimen (3 & 4), Taipingling (5 & 6), and Zhuanghe (1 & 2)[7]
Reactor data
[edit]| Unit | Type | Net Capacity MWe |
Gross Capacity MWe |
Construction start | First
criticality |
Grid
connection |
Operation start | Notes |
|---|---|---|---|---|---|---|---|---|
| Phase I | ||||||||
| 1 | Hualong One | 1116 | 1200 | 2019-12-26 | 2026-02-03 | 2026-02-13 | 2026-04-19 | [8] |
| 2 | Hualong One | 1116 | 1200 | 2020-10-15 | 2026-06-25 | 2026-07-04[9] | 2026-08-03 | [10] |
| Phase II | ||||||||
| 3 | Hualong One | 1116 | 1200 | 10 Jun 2025 | 2029 | [11] | ||
| 4 | Hualong One | 1116 | 1200 | 10 May 2026 | 2030 | [12][13] | ||
| Phase III | ||||||||
| 5 | Hualong One 2.0[7] | 1116 | 1200 | |||||
| 6 | Hualong One 2.0[7] | 1116 | 1200 | |||||
See also
[edit]References
[edit]- ↑ "Nuclear Power in China". Information Papers: Country Profiles. World Nuclear Association (WNA). 11 June 2025. Retrieved 12 June 2025.
- ↑ "First Taipingling unit enters commercial operation". World Nuclear News. 20 April 2026. Retrieved 21 April 2026.
- ↑ "China approves construction of four new reactors". World Nuclear News. 3 January 2024. Retrieved 11 January 2024.
- ↑ "Construction under way of third Taipingling unit". World Nuclear News. 11 June 2025. Retrieved 12 June 2025.
- ↑ "Second Taipingling unit begins supplying power". World Nuclear Association (WNA). 6 July 2026. Retrieved 6 July 2026.
- ↑ "Hualong One nuclear power unit starts operation in south China". People's Daily Online. 4 August 2026. Retrieved 3 August 2026.
- 1 2 3 "China approves construction of eight more reactors in 2026". World Nuclear News. 3 August 2026. Retrieved 3 August 2026.
- ↑ "TAIPINGLING-1". Power Reactor Information System (PRIS). International Atomic Energy Agency (IAEA). 2026-04-20. Retrieved 21 April 2026.
- ↑ "Second Taipingling unit begins supplying power". World Nuclear News. 2026-07-06.
- ↑ "TAIPINGLING-2". PRIS. IAEA. Retrieved 2026-07-08.
- ↑ "TAIPINGLING-3". PRIS. IAEA. 2025-06-24. Retrieved 24 June 2025.
- ↑ "Construction begins on fourth Taipingling unit". World Nuclear News. 11 May 2026. Retrieved 11 May 2026.
- ↑ "TAIPINGLING-4". PRIS. IAEA. 2025-07-06. Retrieved 7 July 2025.